Friday, October 17, 2008

The installation of the 1st lighthing fixture

17th October 2008

The construction work at the site was working in full swing today. This afternoon, I had the opportunity to meet the construction manager for the ceiling design. Fortunately he suggested that I should meet with the ceiling man for further recommendation and advice. Thanks Mr. Thomas for giving me his number. At the same time, the electrician was also at the site to fix the spotlight below the concrete gutter before the workers dismantled the timber scaffolding. The window frame at the main entrance was also being installed. The workers also started installing the wall tiles in the kid's bathrooms.

This picture was taken yesterday

The house taken yesterday from the right side

Close up of Mr. Misbah smoothening the 2nd pole yesterday

The window frame at the main entrance delivered and ready to be installed

Mr. Thomas making some important phone call outside Syafi's bathroom

Close up of Syafi's bathroom tiles

Mr. Peter installing the spotlight at the back of the house

Close up of the spotlight

Mr. Misbah working on the 3rd pole this afternoon

Another shot of Syafi's bathroom


Safiya's bathroom tiles

The kid's bathroom at the back of the house

Three type of works working simultaneously i.e. Smoothening the 3rd pole at the main entrance, installation of the roof tiles and installing the spotlight at the left side of the house.

The main car porte

The roof tiles are almost complete

The window frame at the main entrance not yet fully installed. They may have to continue this again by tomorrow.

Close up of the spotlight at the front of the house outside Syafi's bedroom

No comments: